Korra Energies - Waste Heat Recovery power plant for Helwan Cement Factory

Sectors
Country
Services
Korra-Energi is working on an IN-HAND project of a Waste Heat
Recovery power plant for Helwan Cement Factory and has invited Diar
Consulting Group to design the FF system for the STG building

The project scope of work in detail, which includes as a minimum the following: 

1. Firefighting Works: 
•        Firefighting design drawings for the control section in the STG building. 
•        Firefighting design drawings for the turbine section in the STG building. 
•        Special fire suppression system design needed for electrical and control rooms. 
•        Pump room and related tank design drawings. 
•        Preparing BOQ and specification of the designed systems. 
•        Verification of the firefighting system as of tie-in point to the turbine building 
•        Recalculate the fire system as of pump head and flow with related specifications.

2. Fire Alarm Works: 
•        Fire alarm design drawings for the control section in the STG building. 
•        Fire alarm design drawings for the  turbine section in the STG building. 
•        Special fire detection suppression system design needed for electrical
         and control rooms.
•        Pump room and related tank design drawings. 
•        Preparing BOQ and specification of the designed systems