Project Brief:
SHell company intent to make an extention to it's oil Lubricant palnt located in 6 of October city this extention was include the following:
2 new storage tanks with nominal capacity of ~ 250 ton/each one will be accommodating Additives LUBAD 1397 and other accommodating GTL base oil wiith a dedicated pump for each tank.
►process & utility Piping and pipe racks/supports required to serve all new facilities.
►8” HDPE Storm water/ oily water Drainage line for the two tanks & shredder, and tie-in to existing oily system.
►required heat tracing system.
►Two Truck Sample points’ collection Steel structure platforms.
Diar Scope of Work:
This should cover (but not limited to) the following:
- Installing 2 new storage tanks with nominal capacity of ~ 250 ton/each.
- One will be accommodating Additives LUBAD 1397 and other
accommodating GTL base oil.
- Installing a dedicated pump for each tank.
- Installing process & utility Piping and pipe racks/supports required to
serve all new facilities.
- Installing 8” HDPE Storm water/ oily water Drainage line for the two
tanks & shredder, and tie-in to existing oily system.
- Installing required heat tracing system.
- Apply painting and insulation.
- Two Truck Sample points’ collection Steel structure platforms.
FEED & Detailed engineering services Design for LOBP 6th October
Plant including the following:
• Process Engineering
• Piping Engineering and 3D modeling
• Instrumentation and Control
• Electrical Engineering
• Mechanical and Tanks Design
• Machinery
• Civil and Structural Engineering
In addition to the site supervision for all disciplines and construction
management by Diar consulting group.